Relocation of Mossini Press Line in Bielsko-Biała

Protech Motors proudly presents the successful completion of the Mossini mechanical and hydraulic press line relocation project, with a total weight of 800 tons, carried out in Tychy, Silesian Voivodeship. This complex project involved disassembly, loading, transport, and reassembly in a new location, requiring precise planning and advanced logistics.

Project Phases:

  1. Disassembly and Loading: The Mossini press line was disassembled and prepared for loading onto a 240-ton capacity hydraulic self-propelled platform, ensuring safe transportation from the plant.
  2. Oversized Transport: The equipment was transported to the new location using specialized oversized transport vehicles.
  3. Unloading and Reassembly: Upon arrival, the presses were unloaded and reassembled in the new facility, restoring their full functionality.

Project Significance:
This project highlights our expertise in the precise relocation of heavy industrial equipment, emphasizing safety, efficiency, and minimizing production downtime. Our modern fleet, including self-propelled platforms and specialized vehicles for oversized transport, enabled the seamless execution of the project, adhering to the highest industry standards.

Our Commitment:
At Protech Motors, we are dedicated to delivering high-quality services on every project. With 25 years of experience and a wide range of specialized services, we are ready to tackle even the most demanding challenges in the industrial sector.

 

 

Two orange ORMIG cranes lifting a heavy Mossini press line component during relocation in Bielsko-Biała.
Two ORMIG cranes lifting a large Mossini press component with slings during the line relocation.
Two orange ORMIG cranes moving a heavy Mossini press component inside a production hall.
Orange ORMIG crane positioning a heavy Mossini press component on an SPMT platform during relocation in Bielsko-Biała.
SPMT platform transporting a heavy Mossini press component during the line relocation in Bielsko-Biała.
SPMT platform positioning a heavy Mossini press component beside a hydraulic gantry system.
Hydraulic gantry system lifting a heavy Mossini press component during the line relocation.
Hydraulic gantry system positioning a Mossini press in its prepared foundation inside a production hall.
ORMIG crane and hydraulic gantry system working on the installation of a Mossini press inside a production hall.
Hydraulic gantry system lifting a Mossini press frame while positioning it in the foundation.